Engineering Projects Update- July 2019
Andre Monnot, P.E.
Sewer Rehabilitation Program:
Gravity Collection Rehabilitation Project is advertised for bids, bid opening scheduled for July 17th.
Lift Station Rehabilitation Project is 60% design complete, opinion of construction cost remains within $1,799,700 budget.
Same as last report:
Construction contingency of $100,900 is held in reserve (expect to spend in the gravity collection rehab project).
Utility GIS website is complete and operational. When parcel data is complete, consultant will schedule training with Town and make website public.
Pearl St. Lift Station Force Main has been approved by LA Dept. of Health, and is ready for construction
Harrison Extension: No change. Corps of Engineers Jurisdictional Determination received. Much of alignment is considered wetland, as expected.
DOTD Utility Extension: All Town work complete. WST electrical service completed last week.