Engineering Projects Update- June 2019

June 18, 2019

Andre Monnot

 

Sewer Rehabilitation Program:

  • Gravity Collection Rehabilitation Project is advertised, bids will be opened on July 10th.

  • Lift Station Rehabilitation Project is 55% design complete, opinion of construction cost remains within $1,799,700 budget. 

  • Same as last report:

    • Construction contingency of $100,900 is held in reserve (expect to spend in the gravity collection rehab project).

    • Utility GIS website is complete and operational.  When parcel data is complete, consultant will schedule training with Town and make website public. 

    • Pearl St. Lift Station Force Main has been approved by LA Dept. of Health, and is ready for construction

       

       

       

       

       

       

       

       

       

Sewer Rehabilitation Budget Status June 19

 

 

Harrison Extension: No change. Corps of Engineers Jurisdictional Determination received. Much of alignment is considered wetland, as expected.

 

DOTD Utility Extension: No change. All Town work complete. Pump station startup will be conducted after WST brings new service.

 