Engineering Projects Update- August 2018

August 21, 2018

Jean Thibodeaux

Abita Oaks Loop Parking:  Developer/HOA adding 11 off-street parking spots and a playground area.  Under construction, 70% complete

Recreational Trails:  Project pending US Army Corps of Engineers “Waters of the US” permit review.  Following up with USACE on status.

Abita Trailhead Park:  Additional parking conceptual plan complete and the cost estimate is being developed.

Andre Monnot

Sewer Rehabilitation Program: CCTV inspection report received two weeks ago, late due to data loss by consultant & required re-inspection.  Basis of design document expected mid-September. 

 

Harrison Ave Extension Land Use and Transportation Study: Regional Planning Commission Report is complete.  Next phase of the effort will begin in September, including environmental and engineering advancement of the concept.

 

Utility Service to LADOTD: Design is complete, permits issued, and DOTD agreement executed for extension of approx. 1,500 LF of 10” Water Main, a new sewer lift station, and 1,500 LF of 2” SFM,  Construction of the water main will commence in early September.  The total project time is approx. 90 days.

 

 

View Spreadsheet - Sewer System Rehab Project Budget Status

 

 

 

 