Engineering Projects Update- August 2018


Jean Thibodeaux

Abita Oaks Loop Parking: Developer/HOA adding 11 off-street parking spots and a playground area. Under construction, 70% complete Recreational Trails: Project pending US Army Corps of Engineers “Waters of the US” permit review. Following up with USACE on status. Abita Trailhead Park: Additional parking conceptual plan complete and the cost estimate is being developed.

 

Andre Monnot

Sewer Rehabilitation Program: CCTV inspection report received two weeks ago, late due to data loss by consultant & required re-inspection. Basis of design document expected mid-September.

Harrison Ave Extension Land Use and Transportation Study: Regional Planning Commission Report is complete. Next phase of the effort will begin in September, including environmental and engineering advancement of the concept.

Utility Service to LADOTD: Design is complete, permits issued, and DOTD agreement executed for extension of approx. 1,500 LF of 10” Water Main, a new sewer lift station, and 1,500 LF of 2” SFM, Construction of the water main will commence in early September. The total project time is approx. 90 days.

Featured Posts
Recent Posts
Archive
Search By Tags
bottom of page