September 17, 2019

Andre Monnot, P.E.

Engineering Report for September:

Sewer Rehabilitation Program:

  • Gravity Collection Rehabilitation Project contract will be executed within several days, construction expected in 60 days.  Low bid is at approx. $2.4 M (estimated cost was $3.0 M), all...

August 20, 2019

Principal Engineering recommends award of the gravity sewer rehabilitation project bid to Gulf Coast Underground, LLC.  The amount of the lowest responsive bid is $2,423,360.80.  All aspects of the low bid appear to be in order. 

July 17, 2019

Andre Monnot, P.E.

Sewer Rehabilitation Program:

  • Gravity Collection Rehabilitation Project is advertised for bids, bid opening scheduled for July 17th.  

  • Lift Station Rehabilitation Project is 60% design complete, opinion of construction cost remains within $1,7...

June 18, 2019

Andre Monnot

Sewer Rehabilitation Program:

  • Gravity Collection Rehabilitation Project is advertised, bids will be opened on July 10th.

  • Lift Station Rehabilitation Project is 55% design complete, opinion of construction cost remains within $1,799,700 budget. 

  • ...

April 25, 2019

Andre Monnot

Sewer Rehabilitation Program:

  • Gravity Collection Rehabilitation Project is 100% design complete.  LDEQ (funding agency) has reviewed and approved for advertisement.  When final comments from LADOTD for pavement patching, and clearance from LADH are recei...