- Feb 28, 2018
Update- Grover & Laurel
SEWER PROJECT UPDATE Grover and Laurel- cleaning and CCTV.


- Feb 27, 2018
Earth Fest Volunteer Information
10TH ANNUAL ABITA SPRINGS 2018 EARTH FESTIVAL Saturday, March 24, 2018, noon to 4 ABITA SPRINGS TRAILHEAD Entry is free. COMFORTABLE SHOES and SUNSCREEN recommended. Festival is a rain or shine event. If there are dangerous winds or lightning predicted, decision to cancel will be made by 10 a.m. and posted on Friends of the Park facebook page or at abitapark.com. Festival will include green vendors, information booths, activities for kids, food, live music, a tree and plan
- Feb 27, 2018
Update- Grover & Cypress
SEWER PROJECT UPDATE Grover St. and Cypress St. - CCTV work again today.
- Feb 26, 2018
Update- St. Charles St.
REVISED Update
Sewer Project
Due to weather over the weekend we are unable to work where previously scheduled. Will be moving to Saint Charles street working on lift station 2 StartFragment
- Feb 23, 2018
Update- Grover & Cypress
SEWER PROJECT UPDATE Grover St. and Cypress St. is were they will start CCTV work today.
- Feb 22, 2018
Sewer Project Update- Andrew Street
SEWER PROJECT UPDATE
They will begin doing CCTV work on Andrew Street today.
- Feb 21, 2018
Sewer Project Update- Pine Street
Sewer Project Update They will be continuing CCTV Inspections on Pine Street. This work identifies:
Root intrusion
Pipe cracking
Offset joint pipes
Corrosion
Deterioration over time
Poor installation or previous repair efforts
Accidental puncturing
Severe blockage

- Feb 20, 2018
Engineering Projects Update- February 2018
Jean Thibodeaux Railroad Avenue - Contractor has ordered material and construction will start when the material arrives.
Recreational trails - Project permit application is being review by the US Army Corps of Engineers. We expect to receive the permit in February, but they may be delayed until March.
Abita Meadows - Currently in Final Stage Review and up for Preliminary approval. The majority of final stage comments have been addressed. Drainage maintenance - Developed

- Feb 19, 2018
Gravel and Grade Schedule
All gravel roads in the city limits of Abita Springs will be graded during the 1st and 3rd quarter of the calendar year. To report needed maintenance please visit our reporting page.
- Feb 16, 2018
Sewer Project Update- Villas at Abita
Sewer Project Update They will be continuing CCTV Inspections on Linda Lou and Dundee Loop N and S.